SIGNUM -81
Payment Plan
On Booking
:
10%
Within 45 Days of booking
:
10%
On Start of Excavation
:
12.5 % of BSP
Within 6 Months after Excavation or
Or Completion of Foundation (Whichever is later)
:
10 % of BSP + 25 % (EDC/IDC)
Within 12 Months after Excavation
Or Casting of Ground Floor Roof (Whichever is later)
:
10 % of BSP + 25 % (EDC/IDC)
Within 18 Months after Excavation
Or Casting of First Floor Roof (Whichever is later)
:
10 % of BSP + 25 % (EDC/IDC)
Within 24 Months after Excavation Or Casting of Second Floor Roof
(Whichever is later)
:
10 % of BSP + 25 % (EDC/IDC)
Within 30 Months after Excavation Completion of Electrical
Conduiting (Whichever is later)
:
10 % of BSP
Within 36 Months after Excavation Or Installation of Shuttering
(Whichever is later)
:
12.5 % of BSP
On Offer of Possession
:
5 % + Other Charges (If Any)
*Terms & Conditions :-
* Cheque in favor of Manira Developers Pvt. Ltd.
* Service Tax as applicable will be charged extra.
* Any taxes levied by the government will be charged as per actual.